The Arena
Oracle cites force majeure on Project Jupiter as 2028 slips
Oracle has spent the week telling investors its AI backlog is real. On Thursday it told the developer of its largest New Mexico campus that it may stop paying for it. Oracle shares fell 4% after Bloomberg reported the company sent a force majeure notice to Blue Owl Capital, the developer behind Project Jupiter, aiming to delay payments on the 2.45-gigawatt campus if it does not come online as expected in 2028. A force majeure clause is the contract language for hurricanes and wars — events nobo